Council accepted the Master Plan for the Town Center in March 2014 and WRNS Architects was hired for the design shortly after. Competitive bids for the project were received in February 2019 and the Ground Breaking was held on April 23, 2019. On December 11, 2021, we held the Ribbon Cutting Ceremony at the new Town Center. We posted all the photos to the gallery - Click Here.
Project Statistics
Overall Project Design Cost - $7.5 MIL (est.)
Overall Project Construction Cost - $49 MIL (est.)
Overall Project Square Footage - 43,000 SF
Overall Project Site Area - 5 acres
City Hall/PD/Council Square Footage - 31,000 SF
Library Square Footage - 12,000 SF
To learn more about the project read the Atherton Town Center project page - Click Here.