As part of the Peninsula Corridor Electrification Project, Calitrain and its Contractor, Balfour Beatty, will be installing foundations in the vicinity of the Watkins Avenue rail crossing. Construction crews will utilize on-track foundation trains that will require the crossing closure to comply with safety regulations. The Watkins Avenue Rail Crossing will be closed beginning at 8 pm Saturday November 3, 2018, and will be reopened by 6 am Sunday, November 4, 2018. Please use alternate routes. Detour signage will be posted directing traffic to Fair Oaks Avenue during the closure.
For additional questions and information regarding the project, please call the Caltrain project information line at 650-399-9659 or toll free at 800-660-4287. Town staff can be reached at 650-752-0541.