May 5, 2014
To: All Atherton Residents,
Subject: 2014 Spring Patching Project (Project #56057)
The Town of Atherton has contracted Half Moon Bay Grading & Paving for the 2014 Spring Patching Project. The contractor is contracted to perform asphalt concrete pavement base failure repair (patching) in your neighborhood. Weather permitting, work will starts on Tuesday, May 13th and the completed date is Tuesday, May 27th. Work hours are between 8 AM – 5 PM.
During this time, you will experience some delays including traffic detours and roadway detours.
Residents and household staffs will be provided access to their property at all times.
Construction start date Tuesday, May 13th
Day #1, #2 and #3
Dig outs #1-19 and #49-50 (Logan, Patricia, Stockbridge, Lloyden)
Day #4, #5 and #6Dig outs #20-48 (Elena Avenue)
Day #7, #8, #9 and #10
Dig outs #51-76 (Virginia, Oak, Encinal, Magnolia, Encino, Fair Oaks and Ringwood)
For additional questions and information, please contact the Public Works Department at 650-752-0570.
Street Patching List