Town Center Project Activity Blog

This is a Blog for the Civic Center Project. Entries involve updates to the project, photos, video links, and other information relevant to the Project. 

View All Posts

May 23

General Project Updates

Posted on May 23, 2019 at 11:32 AM by grodericks grodericks

January 2019

In an effort to keep everyone updated on the progress of the Town’s Civic Center project, the following are some recent key accomplishments:

December 19, 2018

January 3, 2019

  • Staff posted the Civic Center bid documents to begin the public bidding process on the Town’s website: http://www.ci.atherton.ca.us/bids.aspx?bidID=64 and numerous other contractor sites. Bids are due on Wednesday, February 13, 2019. Staff and the design team will be responding to requests for information (RFI’s) until one week prior to bids being due.

January 16, 2019

January 23, 2019

January 28, 2019

  • Central Valley Environmental (CVE) the contractor that demolished and removed the Library, began demolition and removal of the old Permit Center trailer, Public Works metal office building and removal of the emergency generator. This work was completed on January 31, 2019.

January 30, 2019

  • At the At the request of 3 potential bidders, staff extended the bid response deadline from February 13th to 2 PM on February 27.

Contact for this project is:

Marty Hanneman, P.E.

Project Manager

Town of Atherton

91 Ashfield Road

Atherton, CA 94027

Cell: (916) 804-0336

Email: mhanneman@ci.atherton.ca.us