November 13, 2018
The anticipated schedule for the abatement and demolition of the library.
- Mobilize 1 day: Tue 11/13/18
- Fence Installation & screening 1 day: Tue 11/13/18
- Tree Protection 1 day: Tue 11/13/18
- Library Abatement 4 days: Tue 11/13/18 to Fri 11/16/18
- Structure Separation 1 day: Fri 11/16/18
- Structure Demolition 3 days: Mon 11/19/18 to Wed 11/21/18
- Foundation Demolition 5 days: Mon 11/26/18 to Fri 11/30/18
- Site Grading 2 days: Mon 12/3/18 & Tue 12/4/18
- Capping Utilities 2 days: Wed 12/5/18 & Thu 12/6/18
- Site Clean Up 2 days: Fri 12/7/18 & Mon 12/10/18
There will be no work on Thursday & Friday (Thanksgiving & day after) November 22 & 23. Hours of work will be 8 AM to 5 PM – with no weekend work allowed.
Contacts for this project are:
Town of Atherton Staff Members
Marty Hanneman, Project Manager or David Huynh, Construction Manager