Atherton Avenue Improvements
Atherton Avenue Bicycle Lanes Improvement Project
The Town of Atherton intends to implement the Atherton Avenue Bicycle Lanes project from the Bicycle & Pedestrian Master Plan. The Town has retained a consultant to prepare a grant funding application in conjunction with a consultant from C/CAG to pursue the Active Transportation Program (ATP) Cycle 4 grant, which is composed of federal funds, State SB1(gas tax) and State Highway Account (SHA) funds. The project focuses on improving access for students, families, residents and visitors biking along Atherton Avenue between Alameda De Las Pulgas and El Camino Real. Specific improvements include widening the roadway, improving shoulder conditions, restriping with class II bike lanes, improved crossings at conflict zones, and increasing signage/wayfinding to provide improved bike paths.
If the Town’s grant application is successful, the Town will be looking to retain a consultant to design the Class II bike lane improvements. The design and construction of Class II improvements will include the placement of bike route signs and bicycle lane markings on the pavement. These improvements will help inform users that the routes are designated for use of bicycles. Below is a grant application schedule list and scope of work.
The Town is seeking your input on the proposed project. Please send your comments on the conceptual layout to: nbosan@interwestgrp.com.
History & Status
The Town's consultants will be developing the ATP Cycle 4 application for the Atherton Avenue bicycle facilities improvements this July. The Town will be sending out notifications to Atherton residents regarding this project to request input and determine any concerns regarding the proposed improvements. Listed below is the anticipated schedule of the anticipated milestone and approval of the ATP Cycle 4 Grant. The schedule is subject to change and will be updated as needed, due to unforeseen delay issues.
May 16 – ATP Cycle 4 Call-for-Projects
June 7 – Atherton Bicycle and Pedestrian Advisory Committee (BPAC) Meeting
June 15 – Consultant assigned to Atherton by C/CAG
July 6 – Atherton Avenue Concept Plan posted in link below
July 10 – Atherton Transportation Committee Meeting
July 31 – ATP Grant Application Deadline
December 31, 2018 – Statewide project funding recommendations posted by California Transportation Commission (CTC)
January 2019 – CTC adopts the statewide selected projects
February 15, 2019 – Additional programming recommendations due from Metropolitan Planning Organizations (MPO)
June 2019 – CTC adopts MPO selected projects
Scope of Work
The limits of work for Atherton Avenue Bicycle Lanes Improvements Project are:
- Atherton Avenue – east of Alameda De Las Pulgas and west of El Camino Real
Renderings
Historical Project Materials
June 7, 2018 BPAC Meeting Presentation
Initial Master Plan Project List
Priority Projects List from the Master Plan
February 21, 2018 City Council Staff Report